House first, shed second: Davenport's order of building
Davenport's Land Development Regulations say it plainly: accessory structures "shall not be constructed prior to the principal structure." Just bought a vacant lot inside city limits and want a storage building there for tools while you plan the house? The shed slab has to wait. Build the home, then add the shed.
The code closes the shortcuts too. Shipping containers, Conex boxes, railcar boxes, PODs, semi-trailers, box trucks, trailers and manufactured homes can't serve as accessory buildings in Davenport. That leaves a real shed on a real pad, poured after the house and kept inside the outbuilding cap and the setback lines covered below. Our shed and storage building slab page covers the job countywide, and the Davenport slab contractor page covers bigger buildings in town.

One cap for every outbuilding on the lot
Here's the rule to watch. The city doesn't cap each shed on its own. It caps the total square footage of all accessory buildings on the lot and ties that total to the size of your house. In the R-1 through R-5 districts the cumulative limit is 720 square feet or 50 percent of the principal structure, whichever is less. In AG, RE-1 and RE-2 it's 1,200 square feet or 50 percent, whichever is less.
Do the math for your own lot before you buy a shed. With a 1,300 square foot house in an R district, all outbuildings together top out at 650 square feet. Got a 10x12 shed in the corner already? That's 120 square feet spent, leaving 530 for the new one. A 16x24 storage building at 384 square feet fits. A 20x30 at 600 doesn't. On Residential Estates land, a 2,400 square foot home is the smallest house that unlocks the full 1,200.
Outbuildings count toward the lot's impervious surface and stormwater runoff numbers as well, so a slab uses the same allowance as the roof over it. To confirm your district, check the city's 2025 Official Zoning Map or order its $50 zoning verification letter.

What It Costs
What shed pads run on Davenport lots, priced before we visit.
| Pad | Per sq ft | Typical project | What changes it here |
|---|---|---|---|
| 12x16 storage shed (192 sq ft) | $7 to $12 | $1,344 to $2,304 (our $1,800 project floor applies) | Back-yard access, hand cart or pump |
| 16x20 shop shed (320 sq ft) | $7 to $12 | $2,240 to $3,840 | Thicker slab for a mower or cart |
| 24x30 at the 720 sq ft R-district cap | $7 to $12 | $5,040 to $8,640 | Muck removal, grading, anchor count |
| Any shed or storage building slab | $7 to $12 | $1,800 to $5,000 | Our usual project range |
These are ranges only. Your exact number comes in a free written estimate after we see the site, delivered within 48 hours of the visit.
Easements, buffers, Lake Play and the 50 foot shoreline line
With the size settled, the spot comes next. The city keeps accessory structures out of required buffer strips and public utility easements, and no shed may sit forward of the front building line, or either front line on a corner lot. In residential districts, every accessory building has to stand at least 5 feet from the house and from any other accessory building.
On the water, there's one more line. Under the city's LDR Sec. 2.23.00, nothing but a boat house or dock can be built within 50 feet of the shoreline of a lake or water body 10 feet or wider at normal water level. The city's lake protection rules add a shoreline zone running 50 feet landward of the ordinary high-water line where development is barred with narrow exceptions. Does your back yard slope toward Lake Play, the little lake ringed by a quarter-mile trail off Williams Street, or toward Horse Creek, the stream the town was first named for? If that water is 10 feet or wider at normal level, measure from the shoreline and plan the pad at least 50 feet back.

How the Job Goes
Check the cap
First we add up the outbuildings already on the lot and make sure the new shed fits under Davenport's limit.
Measure the lines
Next we mark the front building line, easements, the 5 foot spacing and any shoreline setback.
Quote in writing
Within 48 hours, you get a written price built from your shed maker's drawing.
Pour and cure
Once the permit is issued, we prep, set anchors, pour and cure the pad ahead of the shed's arrival.
Why a Davenport shed pad isn't a no-permit job
The city does offer a Building Permit Exemption Request, a $40 form for single-family work valued under $7,500. It leaves out structural work, and a slab that carries a building is structural. The city's Building page also lists sheds, pavers and slabs among the submissions that need a site plan showing setbacks from property lines, and City Code Sec. 5-51 requires a permit before structural work of any character.
On the bright side, the fees are small. The city's permit fee is $50 minimum for valuations under $2,500, plus plan review at half the permit fee with a $25 minimum. If a 12x16 pad's valuation lands under that $2,500 line, you pay the city $75. Go over $2,500 and Florida law requires a recorded Notice of Commencement.
Applications go through the city's online Citizen's Engagement portal, with an application signed by the contractor's qualifier or an owner-builder and notarized. When an LLC or corporation owns the property, a contractor has to pull the permit, not the owner. Permitted work has to be finished within six months of issue unless the city grants an extension. The department is listed on the City of Davenport Building and Planning page. Past the city line, Polk County handles it and lists pre-manufactured storage buildings as permit work.
Ridge sand, wet pockets and pour day near Davenport
The city's slogan is "Gateway to the Ridge," and the soil maps agree. In a 43-point sample of NRCS soil mapping inside the 2020 city boundary, about 65 percent of points landed on Candler sand and about 7 percent on Astatula sand, both excessively drained and rated "not limited" for small buildings without basements. On that ground, a shed pad just needs a clean strip, compaction and forms.
The low spots take more work. The same sample turned up Basinger mucky fine sand, Immokalee sand, Smyrna and Myakka fine sands and Samsula muck, each at roughly 2 to 5 percent of points, and every one is rated "very limited" for building. Hit dark organic soil while stripping, and we dig it out and replace it with compacted clean sand. The Polk County Water Atlas also points out that compacted soil sheds water instead of soaking it in, so we grade the yard to carry runoff around the new slab and away from the house.
A standard storage shed gets 4 inches of concrete with fiber or welded wire, and a control joint cut about every 10 feet. We start summer pours early to beat the heat and keep the pad moist for the first few days, since NRMCA puts normal curing at 3 to 7 days. The rainy season, May 25 to October 10 by the National Weather Service's count for West Central Florida, also means we watch the radar the afternoon before.
Tying a Davenport shed down before the storm months
Can a shed be anchored to the slab for hurricanes? Yes, and it should be. Florida law exempts storage sheds of 720 square feet or less from the wind-borne debris impact standards, the same 720 square foot number as the city's accessory cap in the R districts. That exemption is only about debris-impact protection. Wind-load design and tie-downs still apply.
Anchor bolts go into the fresh concrete, or the pad is left ready for drilled anchors, exactly where the shed maker's engineered drawing shows them. On a site-built shed, the designer's sheet sets the layout. The design wind speed for your lot comes from the Florida Building Code's wind maps and belongs on those plans. Hurricane season runs June 1 to November 30, and the National Hurricane Center puts most activity between mid-August and mid-October. Pour in spring or early summer and the shed has time to be set and bolted well before then. Planning a larger farm structure out in the county? See our Davenport pole barn slab page or the guide to Florida's farm building exemption.
Questions We Get
Can I put a shed on my empty lot in Davenport before the house is built?
Do I pour the pad bigger than the shed's floor?
My Davenport lot already has a small shed. Does it count against the new one?
Can I use a shipping container instead of a shed in Davenport?
Does Davenport's $7,500 permit exemption cover a shed slab?
How far from Lake Play or another lake does a Davenport shed have to be?
How does a shed get tied to its pad before hurricane season?
Sources we used
- Unified Land Development Regulations (updated March 2, 2026), City of Davenport
- Building Department, City of Davenport
- Building Permit Exemption Request, City of Davenport
- Code of Ordinances Ch. 5 Buildings (Secs. 5-51, 5-52), City of Davenport (Municode)
- Building & Planning, City of Davenport
- Building Permitting, Polk County Building Division
- Florida Statutes s. 553.73, Florida Legislature
- CIP 11 Curing In-Place Concrete, NRMCA
- Learn More: Soils, Polk County Water Atlas (USF Water Institute)